Case study:Lower Bockhampton

From RESTORE
Jump to navigation Jump to search

This case study is pending approval by a RiverWiki administrator.

Approve case study

 

0.00
(0 votes)


To discuss or comment on this case study, please use the discussion page.


Location: 50° 42' 51.24" N, 2° 23' 41.76" W
Loading map...
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.


Project overview

Edit project overview
Status Complete
Project web site
Themes Fisheries, Habitat and biodiversity, Hydromorphology
Country England
Main contact forename Allan
Main contact surname Frake
Main contact user ID
Contact organisation Environment Agency
Contact organisation web site
Partner organisations
Parent multi-site project

Case_study:River Frome Rehabilitation Plan

This is a parent project
encompassing the following
projects
No
This case study hasn’t got a picture, you can add one by editing the project overview.

Project summary

This case study hasn’t got any project summary, you can add some by editing the project overview.

Monitoring surveys and results

This case study hasn’t got any Monitoring survey and results, you can add some by editing the project overview.

Lessons learnt

This case study hasn’t got any lessons learnt, you can add some by editing the project overview.


Image gallery


ShowHideAdditionalImage.png


Catchment and subcatchment

Catchment

River basin district South West
River basin Dorset

Subcatchment

River name Frome Dorset (Lower) & Furzebrook Stream
Area category 100 - 1000 km²
Area (km2)
Maximum altitude category 200 - 500 m
Maximum altitude (m) 223223 m <br />0.223 km <br />22,300 cm <br />
Dominant geology Calcareous
Ecoregion Great Britain
Dominant land cover Arable and Horticulture
Waterbody ID GB108044009690



Other case studies in this subcatchment: 2e Lower Woodsford River and Floodplain Enhancement, Bockhampton Enhancement, Hurst Bridge (downstream), Louds Mill (Downstream)m Enhancement, Lower Woodsford, Martins River Island, Moreton Channel Gravel Reprofiling, North Channel Upper Reach, River Frome Rehabilitation Plan, Unit 1b - Long Bridge to Downstream of Louds Mill... further results


Site

Name
WFD water body codes GB108044009690
WFD (national) typology
WFD water body name Frome Dorset (Lower) & Furzebrook Stream
Pre-project morphology
Reference morphology
Desired post project morphology
Heavily modified water body No
National/international site designation
Local/regional site designations
Protected species present No
Invasive species present No
Species of interest
Dominant hydrology
Dominant substrate
River corridor land use
Average bankfull channel width category
Average bankfull channel width (m)
Average bankfull channel depth category
Average bankfull channel depth (m)
Mean discharge category
Mean annual discharge (m3/s)
Average channel gradient category
Average channel gradient
Average unit stream power (W/m2)


Project background

Reach length directly affected (m)
Project started
Works started
Works completed
Project completed
Total cost category
Total cost (k€)
Benefit to cost ratio
Funding sources

Cost for project phases

Phase cost category cost exact (k€) Lead organisation Contact forename Contact surname
Investigation and design
Stakeholder engagement and communication
Works and works supervision
Post-project management and maintenance
Monitoring



Reasons for river restoration

Mitigation of a pressure
Hydromorphology
Biology
Physico-chemical
Other reasons for the project


Measures

Structural measures
Bank/bed modifications
Floodplain / River corridor
Planform / Channel pattern
Other
Non-structural measures
Management interventions
Social measures (incl. engagement)
Other


Monitoring

Hydromorphological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Biological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Physico-chemical quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Any other monitoring, e.g. social, economic

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative


Monitoring documents



Additional documents and videos


Additional links and references

Link Description

Supplementary Information

Edit Supplementary Information