Case study:Welwick Managed Realignment Scheme

From RESTORE
Revision as of 10:44, 15 February 2018 by Ascarr (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
0.00
(0 votes)


To discuss or comment on this case study, please use the discussion page.


Location: 53° 39' 0.52" N, 0° 16' 55.97" W
Loading map...
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.


Project overview

Edit project overview
Status Complete
Project web site
Themes Habitat and biodiversity
Country England
Main contact forename Natalie
Main contact surname Frost
Main contact user ID
Contact organisation ABPmer
Contact organisation web site
Partner organisations ABP
Parent multi-site project
This is a parent project
encompassing the following
projects
No
Panoramic view from easterly corner of site

Project summary

Edit project overview to modify the project summary.


Associated British Ports (ABP) constructed a new Roll-on Roll-off terminal at Immingham Outer Harbour (opened in July 2006), which resulted in the direct loss of 22ha of intertidal mudflat area and potentially up to 5ha of indirect losses in a proposed Special Protection Area (pSPA) and a proposed Special Area of Conservation (pSAC). In consultation with regulatory bodies and local nature conservation interest groups, the two managed realignment schemes at Welwick and Chowder Ness were identified as contributing to a potentially acceptable compensation package for the impacts of the Immingham development.

The objective of Welwick was to create between 15 and 38 ha of intertidal mudflat, between 12ha and 28ha of saltmarsh and between 4 ha and 10ha of grassland. Welwick was undertaken for the same purpose as another realignment on the Humber, Chowder Ness, which is presented as a separate case study. Both schemes were designed and implemented by the same organisations (Associated British Ports (ABP) and ABPmer), and to very similar timescales and principles. To inform the final design of these sites, numerical modelling was undertaken based on LiDAR elevation data. This was designed to ensure the correct balance of habitats would be achieved. As mudflat creation was the main objective of the schemes, and as the sites were largely too high for this to occur, the land was re-profiled to increase the extent of lower areas where mudflat could develop (i.e. below Mean High Water Neap (MHWN)) (see Plates 2 and 3 for an illustration of the design steps undertaken). Prior to these works, the land at Welwick had an approximate elevation of 2.8mODN, some 0.4m below the level of the Mean High Water Spring (MHWS) tides. The reprofiling included the creation of a gentle slope from the fronting, existing, mudflats to the rear of the sites.

New flood defences were created at the rear of the 54ha Welwick site to a minimum height of 6.1m Ordnance Datum Newlyn (ODN); designed to withstand a 1 in 50 year design event. A strip of saltmarsh was expected to develop in front of the new defences. The 70,000m3 of material needed for these defences was obtained from within the site from a combination of reprofiling and creation of temporary borrow pits. The new embankment was seeded and left to stabilise for one year.

The existing seawall was removed over a length of 1,400m, and the approximately 20,000m3 of material gained was used to fill the temporary borrow pits. The wholesale removal, rather than the creation of solitary breaches, was chosen for a number of reasons: it improves connectivity with the wider estuary; it more closely recreates the type of environments that existed prior to the land claim; it enables the whole cross sectional area of estuary including the realignment site, to respond to estuary wide changes; and it increases energy levels within the site, thereby improving the likelihood that mudflat habitat will be maintained.

The old defence was removed in a series of stages:

  • (1) removing the rear of the embankment;
  • (2) the rock gabions, and
  • (3) the overall lowering of the embankment. Following this, breaches were created in the existing saltmarsh in front of site. These were required as the fronting marsh is designated, and could thus not be removed completely to increase wave energy even further. As the typical elevation of this marsh was 3.2mODN, which coincides with the MHWS level, these breaches were necessary to allow the site to flood and drain sufficiently. The location of the breaches was chosen to minimise marsh losses (approximately 0.4ha). Their width had been assessed by calculating the discharge and considering the critical threshold for erosion of sediment. The suggested breach size was considered large enough for the velocities to be below the critical threshold for erosion.

As Welwick was considered relatively small-scale in relation to the estuary as a whole any predicted changes to the hydrodynamics and sediment dynamics were expected be extremely localised and relatively small in magnitude (ABPmer, 2003).

Monitoring surveys and results

Edit project overview to modify the Monitoring survey and results.


A ten-year monitoring programme is being undertaken to describe both changes to sites fronting the realignment (in relation to bathymetry, saltmarsh evolution, invertebrates and waterfowl), and to the realignment site itself (in relation to topography, saltmarsh composition, changes to intertidal invertebrates and bird and wildfowl usage).

Invertebrates: The monitoring has shown that invertebrates have colonised this new sediment. In 2009, between 667 and 7,286 organisms were found per m² (belonging to between 5 and 13 species). The abundance, diversity and biomass of species in the mudflat have been increasing since the realignment has been implemented, although these are still typically lower compared to fronting, pre-existing, mudflat sites. This is unsurprising given that the community has still not had much time to establish and develop. Birds: Shorebirds are making good use of the site; overall, numbers observed exceed original predictions. For example, a total of 31 different waterbird species were recorded using the realignment site between September 2008 and March 2009. The site has developed as a major roosting site for wading birds at high water, including red knot, dunlin, curlew and bar-tailed godwit. Birds such as black-tailed godwit and curlew have been using the site with increasing frequency.

Saltmarsh and Grassland: With regards to the development of other habitats, there was a requirement to also create saltmarsh and grassland on site. By 2009, a proportion of the site had developed into saltmarsh, with the typical pioneer plants such as glasswort colonising within one year. Other plants such as common saltmarsh grass, annual sea blite and common cord-grass have been slowly increasing in number. Thus, recognisable saltmarsh plant communities assembled relatively rapidly at Welwick; which was not unsurprising given the proximity of existing saltmarshes (and thus seed sources). With regards to grassland, this was mostly established on the new flood banks, and it appears to be developing the desired species composition. Breeding farmland birds have been found within this habitat. A total of 25 different species were observed during the latest survey undertaken in May 2009, including reed bunting, skylark and yellow wagtail.

Lessons learnt

Edit project overview to modify the lessons learnt.


Accretion: In order for the site to support both mudflat invertebrates and saltmarsh plants, it was important that fine marine sediments were imported into the site, as these provide the ideal environment for intertidal flora and fauna. Furthermore such sediment import would ensure that the site would continue to increase in elevation (i.e. accrete) as sea levels rise. Observations from previous managed realignments has shown that sites can accrete relatively rapidly immediately after a breach, but that elevation increases then tend to level off. At Welwick, site elevation monitoring has so far followed a similar trajectory. To date, overall, the site has increased in elevation with the most notable changes occurring in the initial year following the realignment.


Image gallery


Rear embankment construction and re-profiling at Welwick in 2005
Welwick shortly after seawall removal (i.e. first inundation) in December 2006
Marsh development in the eastern corner – 1 year on and 3 years on


ShowHideAdditionalImage.png


Catchment and subcatchment

Catchment

River basin district Humber
River basin Hull and East Riding

Subcatchment

River name Winestead Drain from Source to Humber
Area category 10 - 100 km²
Area (km2)
Maximum altitude category Less than 100 m
Maximum altitude (m) 3131 m <br />0.031 km <br />3,100 cm <br />
Dominant geology Calcareous
Ecoregion Great Britain
Dominant land cover Arable and Horticulture
Waterbody ID GB104026066570



Site

Name Outer Humber Estuary, East Riding of Yorkshire
WFD water body codes GB104026066570
WFD (national) typology Intertidal
WFD water body name Winestead Drain from Source to Humber
Pre-project morphology
Reference morphology
Desired post project morphology
Heavily modified water body No
National/international site designation
Local/regional site designations
Protected species present No
Invasive species present No
Species of interest
Dominant hydrology Estuary
Dominant substrate Estuarine mud
River corridor land use Arable
Average bankfull channel width category
Average bankfull channel width (m)
Average bankfull channel depth category
Average bankfull channel depth (m)
Mean discharge category
Mean annual discharge (m3/s)
Average channel gradient category
Average channel gradient
Average unit stream power (W/m2)


Project background

Reach length directly affected (m)
Project started
Works started
Works completed
Project completed
Total cost category
Total cost (k€)
Benefit to cost ratio
Funding sources ABP

Cost for project phases

Phase cost category cost exact (k€) Lead organisation Contact forename Contact surname
Investigation and design
Stakeholder engagement and communication
Works and works supervision
Post-project management and maintenance
Monitoring



Reasons for river restoration

Mitigation of a pressure Navigation, compensation for the direct loss of 22ha of intertidal mudflat area
Hydromorphology
Biology
Physico-chemical
Other reasons for the project


Measures

Structural measures
Bank/bed modifications
Floodplain / River corridor
Planform / Channel pattern
Other
Non-structural measures
Management interventions
Social measures (incl. engagement)
Other


Monitoring

Hydromorphological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Biological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative
Invertebrates No Yes Yes Yes No Improvement

Physico-chemical quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Any other monitoring, e.g. social, economic

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative


Monitoring documents



Additional documents and videos


Additional links and references

Link Description

Supplementary Information

Edit Supplementary Information