Case study:River Stour at Glen's weir (Throop fisheries)
Project overview
Status | Complete |
---|---|
Project web site | |
Themes | Fisheries |
Country | England |
Main contact forename | Nick |
Main contact surname | Elbourne |
Main contact user ID | |
Contact organisation | River Restoration Centre |
Contact organisation web site | |
Partner organisations | |
Parent multi-site project | |
This is a parent project encompassing the following projects |
No |
Project summary
The works completed by the Environment Agency contributed to the Stour achieving good ecological status under the Water Framework Directive.
Aims were to:
-increase flow and natural scouring, to encourage self-cleaning of gravels
-enhance existing spawning areas up and downstream of Glens Weir
-increase parr and barbell habitat
-re-instate collapsed banks, re-profile weir pool to increase pool habitats
-provide fly refuge area
-reduce cattle poaching
Dredging in the 1970’s removed thousands of tonnes of gravel to reduce flood risk. This eliminated large areas of spawning habitat for many species of fish. In some places the river has re-naturalised, however routine dredging still takes place downstream as part of the Christchurch flood alleviation scheme. The project aimed to provide new spawning habitat in a previously dredged area. The location was selected based on data gathered by the Environment Agency, The Barbel Society and Ringwood & District Angling Association. Pre-project monitoring work was completed, with post-project monitoring taking place with the help of the RDAA and Barbel Society through catch data, electrofishing and red count data. Around 600 tonnes of Portland stone was used to complete the works; bank stabilisation, old weir structure, flow deflectors and in channel re-profiling. The area was also fenced to prevent cattle poaching, with a gate to allow angler access.
The works have lead to increased flows over the spawning area, and the creation of holding features for larger adult fish. Over 100m of river habitat has been restored. In the past the Stour has often been seen as second best compared with neighbouring rivers but this is now changing.
Monitoring surveys and results
Lessons learnt
Image gallery
Catchment and subcatchmentSelect a catchment/subcatchment
Catchment
Subcatchment
Other case studies in this subcatchment: River Stour at Glen's weir (Throop fisheries)
Site
Project background
Cost for project phases
Reasons for river restoration
Measures
MonitoringHydromorphological quality elements
Biological quality elements
Physico-chemical quality elements
Any other monitoring, e.g. social, economic
Monitoring documents
Additional documents and videos
Additional links and references
Supplementary InformationEdit Supplementary Information
|