Case study:River Kennet Restoration at Durnsford
Jump to navigation
Jump to search
Location: 51° 25' 4.44" N, 1° 30' 27.86" W
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.
Project overview
Status | Complete |
---|---|
Project web site | |
Themes | Habitat and biodiversity, Hydromorphology, Monitoring |
Country | England |
Main contact forename | Nick |
Main contact surname | Elbourne |
Main contact user ID | User:NickRRC |
Contact organisation | River Restoration Centre |
Contact organisation web site | http://www.therrc.co.uk |
Partner organisations | Natural England |
Parent multi-site project | |
This is a parent project encompassing the following projects |
No |
Project summary
Edit project overview to modify the project summary.
Restoration measures implemented along a 2000m section included profile regrading, introduction of large woody debris, removal of invasive species, placement of gravels, cutting trees back, re-connection to adjacent floodplain, creation of wetlands and narrowing of the channel to reintroduce sinuousity.
Monitoring surveys and results
This case study hasn’t got any Monitoring survey and results, you can add some by editing the project overview.
Lessons learnt
This case study hasn’t got any lessons learnt, you can add some by editing the project overview.
Catchment and subcatchment
Select a catchment/subcatchment
Edit the catchment and subcatchment details
(affects all case studies in this subcatchment)
Site
Name | Denford Common |
---|---|
WFD water body codes | |
WFD (national) typology | |
WFD water body name | |
Pre-project morphology | Straight, Embanked, High width:depth |
Reference morphology | Pool-riffle, Sinuous |
Desired post project morphology | |
Heavily modified water body | true |
National/international site designation | |
Local/regional site designations | Area of Special Conservation Interest |
Protected species present | |
Invasive species present | |
Species of interest | |
Dominant hydrology | Quick run-off |
Dominant substrate | Cobble, Estuarine mud, Silt |
River corridor land use | Extensive agriculture |
Average bankfull channel width category | 10 - 50 m |
Average bankfull channel width (m) | |
Average bankfull channel depth category | 5 - 10 m |
Average bankfull channel depth (m) | |
Mean discharge category | |
Mean annual discharge (m3/s) | 9.759.75 m³/s <br />9,750 l/s <br /> |
Average channel gradient category | |
Average channel gradient | |
Average unit stream power (W/m2) |
Project background
Reach length directly affected (m) | 2000 m2 km <br />200,000 cm <br /> |
---|---|
Project started | 2009/10/01 |
Works started | |
Works completed | 2010/03/01 |
Project completed | |
Total cost category | |
Total cost (k€) | |
Benefit to cost ratio | |
Funding sources |
Cost for project phases
Phase | cost category | cost exact (k€) | Lead organisation | Contact forename | Contact surname |
---|---|---|---|---|---|
Investigation and design | |||||
Stakeholder engagement and communication | |||||
Works and works supervision | |||||
Post-project management and maintenance | |||||
Monitoring |
Reasons for river restoration
Measures
Structural measures
| |
---|---|
Bank/bed modifications | Regrading, Introduction of LWD and CWD, Removal of invasive species, Placement of gravels, Cut back of trees, Depth variation |
Floodplain / River corridor | Re-connection to adjacent floodplain, Creation of wetlands |
Planform / Channel pattern | Narrowing, Introduction of sinuousity |
Other | |
Non-structural measures
| |
Management interventions | Management of organic and inorganic sediments |
Social measures (incl. engagement) | Improved public access |
Other |
Monitoring
Hydromorphological quality elements
Element | When monitored | Type of monitoring | Control site used | Result | ||
---|---|---|---|---|---|---|
Before measures | After measures | Qualitative | Quantitative | |||
Flow velocities | Yes | Yes | Awaiting results | |||
Substrate conditions | Yes | Yes | Awaiting results |
Biological quality elements
Element | When monitored | Type of monitoring | Control site used | Result | ||
---|---|---|---|---|---|---|
Before measures | After measures | Qualitative | Quantitative | |||
Fish: Abundance | Yes | Yes | Improvement | |||
Fish: Species composition | Yes | Yes | Improvement | |||
Invertebrates | Yes | Yes | Improvement |
Physico-chemical quality elements
Element | When monitored | Type of monitoring | Control site used | Result | ||
---|---|---|---|---|---|---|
Before measures | After measures | Qualitative | Quantitative |
Any other monitoring, e.g. social, economic
Element | When monitored | Type of monitoring | Control site used | Result | ||
---|---|---|---|---|---|---|
Before measures | After measures | Qualitative | Quantitative |
Monitoring documents
Image gallery
Additional documents and videos
Additional links and references
Link | Description |
---|