|Project completed=2014/10/31 | |Project completed=2014/10/31 | ||
|Total cost category=500 - 1000 k€ | |Total cost category=500 - 1000 k€ | ||
|Total1 cost= | |Total1 cost=965 | ||
|Funding sources=Defra Catchment Restoration Fund | |Funding sources=Defra Catchment Restoration Fund | ||
}} | }} |
Revision as of 09:53, 5 April 2016
Project overview
Status | Complete |
---|---|
Project web site | |
Themes | Economic aspects, Habitat and biodiversity, Hydromorphology, Social benefits, Water quality |
Country | England |
Main contact forename | Mark |
Main contact surname | Watson |
Main contact user ID | |
Contact organisation | WWF-UK |
Contact organisation web site | |
Partner organisations | Coca-Cola, Natural England, Environment Agency, Norfolk Rivers Drainage Board, Castle Acre Fishing Syndicate, West Acre Fishing Syndicate, private landowners, Norfolk Wildlife Trust, Mileham Common Charity Trustees |
This is a parent project encompassing the following projects |
River Nar Castle Acre Common WEG project |
Project summary
Chalk streams are a globally rare and threatened habitat. The Nar is 42 km long, the second longest chalk stream in Norfolk and designated a SSSI. This river catchment is in a rural area with intensive arable farming being the main land use. The upper half of the river flows over chalk, whilst the lower half descends into drained fenland, making the river catchment particularly diverse in form. The river fails to meet the standards of the Water Framework Directive for fish abundance, quantity and dynamics of flow. Poor morphology and poor water quality underpin this failure and require addressing. This project aims to deliver three large-scale reach restorations, improving morphology, water quality, biodiversity and hence ecosystem function.
Monitoring surveys and results
Lessons learnt
Image gallery
Catchment and subcatchmentSelect a catchment/subcatchment
Catchment
Subcatchment
Other case studies in this subcatchment: Castle Acre Rehabilitation Project, Nar SSSI project, Narborough Rehabilitation Project, River Nar Castle Acre Common WEG project, River Nar, Mileham River Restoration Project, West Lexham Rehabilitation Project
Site
Project background
Cost for project phases
Reasons for river restoration
Measures
MonitoringHydromorphological quality elements
Biological quality elements
Physico-chemical quality elements
Any other monitoring, e.g. social, economic
Monitoring documents
Additional documents and videos
Additional links and references
Supplementary InformationEdit Supplementary Information
|