Case study:River Wandle Restoration Project: Difference between revisions
No edit summary |
No edit summary |
||
Line 53: | Line 53: | ||
}} | }} | ||
{{Measures | {{Measures | ||
|Bank and bed modifications measure=Introducting large woody debris, Bank re-grading, Creation of deflectors, Removal of weirs, Habitat diversification, Restoring riparian vegetation | |Bank and bed modifications measure=Introducting large woody debris, Bank re-grading, Creation of deflectors, Removal of weirs, Habitat diversification, Restoring riparian vegetation | ||
|Floodplain / River corridor=Control of invasive species, | |Floodplain / River corridor=Control of invasive species, | ||
|Planform / Channel pattern=Allow future natural channel changes to occur, Assessment and monitoring program, Channel naturalisation; Creation of new meandering channel, Establishment of fish passage, Improvement of channel morphology, Removal of a weir | |Planform / Channel pattern=Allow future natural channel changes to occur, Assessment and monitoring program, Channel naturalisation; Creation of new meandering channel, Establishment of fish passage, Improvement of channel morphology, Removal of a weir | ||
|Social measures=Awareness campaigns, 'Trout in the Town' project raising the awareness of the river's value in schools, Citizen participation in the restoration project, Communication and dissemination program of environmental problems in the area | |Social measures=Awareness campaigns, 'Trout in the Town' project raising the awareness of the river's value in schools, Citizen participation in the restoration project, Communication and dissemination program of environmental problems in the area | ||
|Wider stakeholder / citizen engagement=Public consultation, Participation in works, Participation in maintenance, | |Wider stakeholder / citizen engagement=Public consultation, Participation in works, Participation in maintenance, | ||
}} | }} | ||
{{Hydromorphological quality elements header}} | {{Hydromorphological quality elements header}} |
Revision as of 14:36, 7 August 2013
Project overview
Status | Complete |
---|---|
Project web site | |
Themes | Fisheries, Habitat and biodiversity, Hydromorphology, Monitoring |
Country | England |
Main contact forename | Tim |
Main contact surname | Longstaff |
Main contact user ID | |
Contact organisation | Wandle Trust |
Contact organisation web site | http://www.wandletrust.org/ |
Partner organisations | Environment Agency, Wild Trout Trust |
Parent multi-site project | |
This is a parent project encompassing the following projects |
No |
Project summary
Delivered in three phases on the stretch of the Upper Wandle, referred to as the Carshalton arm, between two public parks, the Grove (upstream) and Wilderness Island (downstream). Phase one works comprised weir notching and the creation of woody debris habitat for fish and invertebrates. The second phase focused on further habitat enhancement and weir removal. Phase three works looking at opportunities along the wider Carshalton section and associated maintenance and monitoring of project works continues in 2012, led by the Wandle Trust.
Monitoring surveys and results
Lessons learnt
Catchment and subcatchment
Edit the catchment and subcatchment details
(affects all case studies in this subcatchment)
Subcatchment:Wandle Other case studies in this subcatchment: River Wandle: Butter Hill Phase 3
Site
Name | Butter Hill, Carshalton |
---|---|
WFD water body codes | GB106039017640 |
WFD (national) typology | Low, Small, Calcareous |
WFD water body name | Wandle (Carshalton Branch at Carshalton) |
Pre-project morphology | Over deepened, Over-widened, Ponded, Straightened |
Reference morphology | Pool-riffle |
Desired post project morphology | |
Heavily modified water body | Yes |
National/international site designation | |
Local/regional site designations | |
Protected species present | No |
Invasive species present | No |
Species of interest | |
Dominant hydrology | Flashy, Artificially regulated |
Dominant substrate | Gravel, Silt, Bedrock |
River corridor land use | |
Average bankfull channel width category | 2 - 5 m |
Average bankfull channel width (m) | |
Average bankfull channel depth category | 0.5 - 2 m |
Average bankfull channel depth (m) | |
Mean discharge category | 1 - 10 m³/s |
Mean annual discharge (m3/s) | |
Average channel gradient category | |
Average channel gradient | |
Average unit stream power (W/m2) |
Project background
Reach length directly affected (m) | 15001,500 m <br />1.5 km <br />150,000 cm <br /> |
---|---|
Project started | 2008/01/01 |
Works started | 2010/01/01 |
Works completed | 2012/09/01 |
Project completed | 2012/12/01 |
Total cost category | |
Total cost (k€) | |
Benefit to cost ratio | |
Funding sources |
Cost for project phases
Phase | cost category | cost exact (k€) | Lead organisation | Contact forename | Contact surname |
---|---|---|---|---|---|
Investigation and design | |||||
Stakeholder engagement and communication | |||||
Works and works supervision | |||||
Post-project management and maintenance | |||||
Monitoring |
Reasons for river restoration
Measures
Structural measures
| |
---|---|
Bank/bed modifications | Introducting large woody debris, Bank re-grading, Creation of deflectors, Removal of weirs, Habitat diversification, Restoring riparian vegetation |
Floodplain / River corridor | Control of invasive species |
Planform / Channel pattern | Allow future natural channel changes to occur, Assessment and monitoring program, Channel naturalisation; Creation of new meandering channel, Establishment of fish passage, Improvement of channel morphology, Removal of a weir |
Other | |
Non-structural measures
| |
Management interventions | |
Social measures (incl. engagement) | Awareness campaigns, 'Trout in the Town' project raising the awareness of the river's value in schools, Citizen participation in the restoration project, Communication and dissemination program of environmental problems in the area |
Other | Public consultation, Participation in works, Participation in maintenance |
Monitoring
Hydromorphological quality elements
Element | When monitored | Type of monitoring | Control site used | Result | ||
---|---|---|---|---|---|---|
Before measures | After measures | Qualitative | Quantitative |
Biological quality elements
Element | When monitored | Type of monitoring | Control site used | Result | ||
---|---|---|---|---|---|---|
Before measures | After measures | Qualitative | Quantitative |
Physico-chemical quality elements
Element | When monitored | Type of monitoring | Control site used | Result | ||
---|---|---|---|---|---|---|
Before measures | After measures | Qualitative | Quantitative |
Any other monitoring, e.g. social, economic
Element | When monitored | Type of monitoring | Control site used | Result | ||
---|---|---|---|---|---|---|
Before measures | After measures | Qualitative | Quantitative |
Monitoring documents
Image gallery
Additional documents and videos
Additional links and references
Link | Description |
---|
Supplementary Information
Edit Supplementary Information