Case study:Meades water garden regeneration project: Difference between revisions
No edit summary |
No edit summary |
||
Line 23: | Line 23: | ||
|Project summary=Two weirs were removed and the site allowed to drain. A temporary dam was built at the top of the site and river flow was piped around the working area. Working from the upstream end, a new channel was dug through the accumulated silt following the line of preferential flow. Nicospan was installed to provide support to the new channel sides and to ensure separation of the silt from the gravel infill, which was imported to form the new river bed. It was important to allow at least 500mm of gravel to provide the depth that chalkstream invertebrates require for their life stage. Excavated silt was distributed around the site within the boundary of old ponds. The new channel was tied into the original course of the river which flowed around the back of the island in the lower pond. A low-lying bund was installed in place of the weir to create a wetland feature. Following completion of the river restoration work, new paths were laid in the gardens and an interpretation board installed. | |Project summary=Two weirs were removed and the site allowed to drain. A temporary dam was built at the top of the site and river flow was piped around the working area. Working from the upstream end, a new channel was dug through the accumulated silt following the line of preferential flow. Nicospan was installed to provide support to the new channel sides and to ensure separation of the silt from the gravel infill, which was imported to form the new river bed. It was important to allow at least 500mm of gravel to provide the depth that chalkstream invertebrates require for their life stage. Excavated silt was distributed around the site within the boundary of old ponds. The new channel was tied into the original course of the river which flowed around the back of the island in the lower pond. A low-lying bund was installed in place of the weir to create a wetland feature. Following completion of the river restoration work, new paths were laid in the gardens and an interpretation board installed. | ||
}} | }} | ||
{{Image gallery}} | |||
{{Case study image | |||
|File name=CS pictDS.png | |||
|Caption=Downstream of the bridge during construction (top) and post-restoration (below) | |||
}} | |||
{{Case study image | |||
|File name=CS pictUS.png | |||
|Caption=Upstream of the bridge, during construction (top) and post-restoration (below) | |||
}} | |||
{{Case study image | |||
|File name=RIMG3386.JPG | |||
|Caption=Established wildlife upstream | |||
}} | |||
{{Case study image | |||
|File name=2007 03 28 (10).JPG | |||
|Caption=Downstream of the bridge prior to project | |||
}} | |||
{{Case study image | |||
|File name=2007 03 28 (17).JPG | |||
|Caption=Upstream of bridge prior to project | |||
}} | |||
{{Image_gallery_end}} | |||
{{Toggle button}} | |||
{{Toggle content start}} | |||
{{Case_study_subcatchment | {{Case_study_subcatchment | ||
|Subcatchment= | |Subcatchment= | ||
Line 120: | Line 144: | ||
{{Monitoring_documents}} | {{Monitoring_documents}} | ||
{{Monitoring_documents_end}} | {{Monitoring_documents_end}} | ||
{{Additional_Documents}} | {{Additional_Documents}} | ||
{{Additional_Documents_end}} | {{Additional_Documents_end}} | ||
Line 170: | Line 172: | ||
}} | }} | ||
{{Case_study_upload}} | {{Case_study_upload}} | ||
{{Toggle content end}} |
Revision as of 06:40, 6 September 2013
Project overview
Status | Complete |
---|---|
Project web site | |
Themes | Habitat and biodiversity, Monitoring, Water quality |
Country | England |
Main contact forename | Nick |
Main contact surname | Elbourne |
Main contact user ID | User:NickRRC |
Contact organisation | River Restoration Centre |
Contact organisation web site | http://www.therrc.co.uk |
Partner organisations | Chiltern Chalk Streams Project |
Parent multi-site project | |
This is a parent project encompassing the following projects |
No |
Project summary
Two weirs were removed and the site allowed to drain. A temporary dam was built at the top of the site and river flow was piped around the working area. Working from the upstream end, a new channel was dug through the accumulated silt following the line of preferential flow. Nicospan was installed to provide support to the new channel sides and to ensure separation of the silt from the gravel infill, which was imported to form the new river bed. It was important to allow at least 500mm of gravel to provide the depth that chalkstream invertebrates require for their life stage. Excavated silt was distributed around the site within the boundary of old ponds. The new channel was tied into the original course of the river which flowed around the back of the island in the lower pond. A low-lying bund was installed in place of the weir to create a wetland feature. Following completion of the river restoration work, new paths were laid in the gardens and an interpretation board installed.
Monitoring surveys and results
Lessons learnt
Image gallery
Catchment and subcatchmentSelect a catchment/subcatchment
Catchment
Subcatchment
Site
Project background
Cost for project phases
Reasons for river restoration
Measures
MonitoringHydromorphological quality elements
Biological quality elements
Physico-chemical quality elements
Any other monitoring, e.g. social, economic
Monitoring documents
Additional documents and videos
Additional links and references
Supplementary InformationEdit Supplementary Information
|