Case study:Compton Island and Meanders: Difference between revisions

From RESTORE
Jump to navigation Jump to search
(Created page with "{{Case study status |Approval status=Draft }} {{Location |Location=51.0611855, -1.5148715999999922 }} {{Project overview |Project title=Compton Island and Meanders |Status=Com...")
 
No edit summary
 
(One intermediate revision by the same user not shown)
Line 6: Line 6:
}}
}}
{{Project overview
{{Project overview
|Project title=Compton Island and Meanders
|Status=Complete
|Status=Complete
|Themes=Flood risk management, Habitat and biodiversity
|Themes=Flood risk management, Habitat and biodiversity
Line 15: Line 14:
|Contact organisation url=www.gov.uk/government/organisations/environment-agency
|Contact organisation url=www.gov.uk/government/organisations/environment-agency
|Multi-site=No
|Multi-site=No
|Project summary=Increase velocities to promote and encourage SSSI chalk stream flora through the construction of 2 in-channel islands
|Project title=Compton Island and Meanders
}}
}}
{{Image gallery}}
{{Image gallery}}
Line 22: Line 23:
{{Case study subcatchment}}
{{Case study subcatchment}}
{{Site}}
{{Site}}
{{Project background}}
{{Project background
|Reach length directly affected=300
|Project started=2018/04/01
|Total1 cost=84,000
}}
{{Motivations}}
{{Motivations}}
{{Measures}}
{{Measures}}

Latest revision as of 12:04, 18 June 2019

This case study is pending approval by a RiverWiki administrator.

Approve case study

 

0.00
(0 votes)


To discuss or comment on this case study, please use the discussion page.


Location: 51° 3' 40.27" N, 1° 30' 53.54" W
Loading map...
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.


Project overview

Edit project overview
Status Complete
Project web site
Themes Flood risk management, Habitat and biodiversity
Country England
Main contact forename Environment
Main contact surname Agency
Main contact user ID
Contact organisation Environment Agency
Contact organisation web site http://www.gov.uk/government/organisations/environment-agency
Partner organisations
Parent multi-site project
This is a parent project
encompassing the following
projects
No
This case study hasn’t got a picture, you can add one by editing the project overview.

Project summary

Edit project overview to modify the project summary.


Increase velocities to promote and encourage SSSI chalk stream flora through the construction of 2 in-channel islands

Monitoring surveys and results

This case study hasn’t got any Monitoring survey and results, you can add some by editing the project overview.

Lessons learnt

This case study hasn’t got any lessons learnt, you can add some by editing the project overview.


Image gallery


ShowHideAdditionalImage.png


Catchment and subcatchment



Site

Name
WFD water body codes
WFD (national) typology
WFD water body name
Pre-project morphology
Reference morphology
Desired post project morphology
Heavily modified water body
National/international site designation
Local/regional site designations
Protected species present
Invasive species present
Species of interest
Dominant hydrology
Dominant substrate
River corridor land use
Average bankfull channel width category
Average bankfull channel width (m)
Average bankfull channel depth category
Average bankfull channel depth (m)
Mean discharge category
Mean annual discharge (m3/s)
Average channel gradient category
Average channel gradient
Average unit stream power (W/m2)


Project background

Reach length directly affected (m) 300300 m <br />0.3 km <br />30,000 cm <br />
Project started 2018/04/01
Works started
Works completed
Project completed
Total cost category
Total cost (k€) 84,00084,000 k€ <br />84,000,000 € <br />
Benefit to cost ratio
Funding sources

Cost for project phases

Phase cost category cost exact (k€) Lead organisation Contact forename Contact surname
Investigation and design
Stakeholder engagement and communication
Works and works supervision
Post-project management and maintenance
Monitoring



Reasons for river restoration

Mitigation of a pressure
Hydromorphology
Biology
Physico-chemical
Other reasons for the project


Measures

Structural measures
Bank/bed modifications
Floodplain / River corridor
Planform / Channel pattern
Other
Non-structural measures
Management interventions
Social measures (incl. engagement)
Other


Monitoring

Hydromorphological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Biological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Physico-chemical quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Any other monitoring, e.g. social, economic

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative


Monitoring documents



Additional documents and videos


Additional links and references

Link Description

Supplementary Information

Edit Supplementary Information