Case study:Ravensbury Park: Difference between revisions
Hazel Wilson (talk | contribs) No edit summary |
No edit summary |
||
(One intermediate revision by the same user not shown) | |||
Line 20: | Line 20: | ||
|Contact organisation=Environment Agency | |Contact organisation=Environment Agency | ||
|Contact organisation url=www.gov.uk/government/organisations/environment-agency | |Contact organisation url=www.gov.uk/government/organisations/environment-agency | ||
|Partner organisations= | |Partner organisations=Environment Agency, Merton Council | ||
|Multi-site=No | |Multi-site=No | ||
|Project summary=Bank naturalisation and enhancements; tree works; backwater enhancement. The river through the park has hard edges which could be enhanced to create more of a marginal edge. Several channels run through the park which could be enhanced to improve their value as wildlife corridors. | |Project summary=Bank naturalisation and enhancements; tree works; backwater enhancement. The river through the park has hard edges which could be enhanced to create more of a marginal edge. Several channels run through the park which could be enhanced to improve their value as wildlife corridors. | ||
Line 41: | Line 41: | ||
|Reach length directly affected=300 m | |Reach length directly affected=300 m | ||
|Project started=2008/01/01 | |Project started=2008/01/01 | ||
|Funding sources=Viridor funding, Thames | |Funding sources=Viridor funding, Thames Water rehabilitation fund | ||
}} | }} | ||
{{Motivations | {{Motivations |
Latest revision as of 13:46, 1 November 2018
This case study is pending approval by a RiverWiki administrator.
Project overview
Status | Planned |
---|---|
Project web site | |
Themes | Fisheries, Social benefits |
Country | England |
Main contact forename | Joanna |
Main contact surname | Heisse |
Main contact user ID | |
Contact organisation | Environment Agency |
Contact organisation web site | http://www.gov.uk/government/organisations/environment-agency |
Partner organisations | Environment Agency, Merton Council |
Parent multi-site project | |
This is a parent project encompassing the following projects |
No |
Project summary
Bank naturalisation and enhancements; tree works; backwater enhancement. The river through the park has hard edges which could be enhanced to create more of a marginal edge. Several channels run through the park which could be enhanced to improve their value as wildlife corridors.
Monitoring surveys and results
Lessons learnt
Image gallery
Catchment and subcatchmentSelect a catchment/subcatchment
Catchment
Subcatchment
Other case studies in this subcatchment: Beddington Park, Beddington Park Enhancements, Boulder Pool and Plough Lane, Durand Close, EDF Weir removal, Eel Pass over tilting weir at Ravensbury Park, Garratt Park, Hackbridge Restoration, Hackbridge weir notch, King Georges Park... further results
Site
Project background
Cost for project phases
Reasons for river restoration
Measures
MonitoringHydromorphological quality elements
Biological quality elements
Physico-chemical quality elements
Any other monitoring, e.g. social, economic
Monitoring documents
Additional documents and videos
Additional links and references
Supplementary InformationEdit Supplementary Information
|