Case study:Lower Aurino river: Molini di Tures riverbed widening

From RESTORE
Revision as of 02:04, 19 March 2013 by A.goltara (talk | contribs)
Jump to navigation Jump to search
0.00
(0 votes)


To discuss or comment on this case study, please use the discussion page.


Location: 46° 53' 1.82" N, 11° 56' 52.09" E
Loading map...
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.


Project overview

Edit project overview
Status Complete
Project web site
Themes Flood risk management, Habitat and biodiversity, Hydromorphology, Monitoring, Spatial planning
Country Italy
Main contact forename Caterina
Main contact surname Ghiraldo
Main contact user ID
Contact organisation Provincia Autonoma di Bolzano
Contact organisation web site
Partner organisations
This is a parent project
encompassing the following
projects
This case study hasn’t got a picture, you can add one by editing the project overview.

Project summary

Edit project overview to modify the project summary.


The Aurino river is a typical Alpine watercourse (basin Area 630 km2, average discharge in summer 30-50 m3/s) subject in the past to a radical channalization (riparap) which reduced significantly the width of the riverbed and the morphological structures and dynamics and which caused a general riverbed lowering and the lost of the connection with the floodplain. In the same time the groundwater lowering caused a loss of the hygrophilous riparian forests (Alnus incana). The riverbed widening of Aurino river in "Molini di Tures" was planned mainly to increase the biodiversity and to invert the riverbed and grounwater lowering process. The work was executed by removing a total of 9.500 m3 of gravel from the disconnected floodplain obtaining a total riverbed windening of 30 m (the double of the extent situation); in the same time the riverbed was reshaped (also by inserting big stones and woody debris and creating new branches) to give it a more natural structure. A monitoring activity was implemented to study the geomorphological and biological effects of the project.

Monitoring surveys and results

This case study hasn’t got any Monitoring survey and results, you can add some by editing the project overview.

Lessons learnt

This case study hasn’t got any lessons learnt, you can add some by editing the project overview.

Catchment and subcatchment

Select a catchment/subcatchment


Edit the catchment and subcatchment details
(affects all case studies in this subcatchment)

Catchment

River basin district Alpi Orientali
River basin Adige

Subcatchment

River name Aurino
Area category 100 - 1000 km²
Area (km2) 630630 km² <br />63,000 ha <br />
Maximum altitude category more than 2000 m
Maximum altitude (m)
Dominant geology
Ecoregion Alps
Dominant land cover Grassland
Waterbody ID



Other case studies in this subcatchment: Lower Aurino master plan, Lower Aurino river: San Giorgio di Brunico riverbed widening


Site

Edit site
Name Molini di Tures
WFD water body codes 03SS3N
WFD (national) typology
WFD water body name D_c Torrente Aurino
Pre-project morphology Single channel
Reference morphology Braided
Desired post project morphology
Heavily modified water body No
National/international site designation
Local/regional site designations
Protected species present Yes
Invasive species present No
Species of interest
Dominant hydrology
Dominant substrate Gravel
River corridor land use Grassland
Average bankfull channel width category 10 - 50 m
Average bankfull channel width (m)
Average bankfull channel depth category 0.5 - 2 m
Average bankfull channel depth (m)
Mean discharge category 10 - 100 m³/s
Mean annual discharge (m3/s)
Average channel gradient category
Average channel gradient
Average unit stream power (W/m2)


Project background

Edit project background
Reach length directly affected (m) 400400 m <br />0.4 km <br />40,000 cm <br />
Project started 2002
Works started
Works completed
Project completed 2013/12/31
Total cost category 50 - 100 k€
Total cost (k€) 100100 k€ <br />100,000 € <br />
Benefit to cost ratio
Funding sources Provincia Autonoma di Bolzano

Cost for project phases

Phase cost category cost exact (k€) Lead organisation Contact forename Contact surname
Investigation and design
Stakeholder engagement and communication
Works and works supervision
Post-project management and maintenance
Monitoring



Reasons for river restoration

Edit reasons for restoration
Mitigation of a pressure Biodiversity increase, flood risk control, morphology restoration
Hydromorphology Width & depth variation, Connection to groundwaters and floodplain
Biology Fish, Invertebrates
Physico-chemical
Other reasons for the project


Measures

Edit Measures
Structural measures
Bank/bed modifications Riverbed widening and diversification
Floodplain / River corridor Floodplain reconnection
Planform / Channel pattern Removal of riprap anc creation of new natural channels
Other
Non-structural measures
Management interventions
Social measures (incl. engagement) Citizen participation in the restoration project
Other


Monitoring

Hydromorphological quality elements

Edit Hydromorphological
quality elements
Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative
Channel pattern/planform No Yes No Yes No Improvement
Structure & condition of riparian/lake shore zones No No No Yes No Improvement

Biological quality elements

Edit biological
quality elements
Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative
Invertebrates No Yes No No Yes No change

Physico-chemical quality elements

Edit Physico-chemical
quality elements
Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Any other monitoring, e.g. social, economic

Edit Other responses
Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative


Monitoring documents

Upload monitoring documents



Image gallery


Foto1 Aurino light.jpg
Foto3 Molini2008 light.jpg


Additional documents and videos

Upload additional documents


Additional links and references

Edit links and references
Link Description

Supplementary Information

Edit Supplementary Information