Case study:Regeneration of the banks of the river Mape

From RESTORE
Revision as of 09:30, 29 September 2014 by JoshRRC (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
0.00
(0 votes)


To discuss or comment on this case study, please use the discussion page.


Location: 43° 22' 55.77" N, 2° 42' 30.97" W
Loading map...
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.


Project overview

Edit project overview
Status Complete
Project web site
Themes Environmental flows and water resources, Habitat and biodiversity, Hydromorphology, Social benefits
Country Spain
Main contact forename City council of Busturia
Main contact surname City council of Busturia
Main contact user ID
Contact organisation City council of Busturia
Contact organisation web site
Partner organisations
Parent multi-site project
This is a parent project
encompassing the following
projects
No
Project picture

Project summary

Edit project overview to modify the project summary.


The main land use is intensive forest exploitation but the territory is fragmented among private owners. Carrying out Inappropriate forestry practices promotes soil loss (erosion problems). Allochthonous species are also found on the banks, such as pines and eucalyptus. The sediment transport negatively affects Urdabai estuary. They are also quite frequent flooding in the neighborhoods that are located in the flood plain at the mouth of the estuary. The main objective of this project is the maintenance and enhancement of biodiversity and ecological status of the banks to fulfill their ecological and social functions. The project has a total budget of 300.000€ and is financed by the Consejería of Environment.

Monitoring surveys and results

This case study hasn’t got any Monitoring survey and results, you can add some by editing the project overview.

Lessons learnt

This case study hasn’t got any lessons learnt, you can add some by editing the project overview.


Image gallery


Aerial view of Mape River and its mouth in Oka River
Mape River as it passes through Busturia in 2008
Mape riverbanks
ShowHideAdditionalImage.png


Catchment and subcatchment

Catchment

River basin district C.H.Cantábrico
River basin Oka

Subcatchment

River name Mape
Area category 10 - 100 km²
Area (km2) 26 km²2,600 ha <br />
Maximum altitude category Less than 100 m
Maximum altitude (m)
Dominant geology
Ecoregion Ibero-Macaronesian
Dominant land cover Urban, Woodland
Waterbody ID



Site

Name Tramo bajo del río Mape
WFD water body codes
WFD (national) typology
WFD water body name
Pre-project morphology Sinuous
Reference morphology Sinuous
Desired post project morphology
Heavily modified water body
National/international site designation
Local/regional site designations
Protected species present
Invasive species present
Species of interest
Dominant hydrology
Dominant substrate
River corridor land use
Average bankfull channel width category
Average bankfull channel width (m)
Average bankfull channel depth category
Average bankfull channel depth (m)
Mean discharge category
Mean annual discharge (m3/s)
Average channel gradient category
Average channel gradient 0.0085
Average unit stream power (W/m2)


Project background

Reach length directly affected (m) 6000 m6 km <br />600,000 cm <br />
Project started 2008/01/01
Works started
Works completed 2010/01/01
Project completed
Total cost category 100 - 500 k€
Total cost (k€) 300 k€300,000 € <br />
Benefit to cost ratio
Funding sources Department of Environment

Cost for project phases

Phase cost category cost exact (k€) Lead organisation Contact forename Contact surname
Investigation and design
Stakeholder engagement and communication
Works and works supervision Department of Environment
Post-project management and maintenance
Monitoring



Reasons for river restoration

Mitigation of a pressure
Hydromorphology Structure & condition of riparian zones
Biology
Physico-chemical
Other reasons for the project


Measures

Structural measures
Bank/bed modifications Revetmens with local species
Floodplain / River corridor Removal of exotic plants
Planform / Channel pattern
Other
Non-structural measures
Management interventions Custody of territory
Social measures (incl. engagement) Recovering the historical and cultural heritage linked to the river
Other


Monitoring

Hydromorphological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Biological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Physico-chemical quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Any other monitoring, e.g. social, economic

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative


Monitoring documents



Additional documents and videos


Additional links and references

Link Description

Supplementary Information

Edit Supplementary Information