Case study:River Avon Our Water Environment: Difference between revisions
No edit summary |
No edit summary |
||
Line 14: | Line 14: | ||
|Partner organisations=Spey Fisheries Board, Cairngorms National Park Authority, Crown Estate Scotland, Delnabo Estate, Fordmouth Farm | |Partner organisations=Spey Fisheries Board, Cairngorms National Park Authority, Crown Estate Scotland, Delnabo Estate, Fordmouth Farm | ||
|Multi-site=No | |Multi-site=No | ||
|Project picture=Fordmouth.jpeg | |||
|Picture description=Engineered woody structure along river bank at Fordmouth Farm - soil scrapped back & 8m long tree trunks, with intact root plates towards river, located along bank prior to burying | |||
|Project summary=River restoration works have been carried out along a high-energy reach of the River Avon within the River Spey Special Area of Conservation (SAC) in Cairngorms National Park. The project encompasses green engineering woody structures and sediment management, as well as water margin management and riparian planting. The aim is to improve the capability of the watercourse to cope with high flow events, reduce excessive erosion and to protect in-channel and riparian habitats, as well as farm livelihoods. The works were carried out as a Scottish Rural Development Programme (SRDP) Agri-Environment Climate Scheme (AECS), supported and managed by a National Lottery Heritage Funded partnership (TGLP) as part of their wider ‘Our Water Environment’ project running across the Tomintoul and Glenlivet area. | |Project summary=River restoration works have been carried out along a high-energy reach of the River Avon within the River Spey Special Area of Conservation (SAC) in Cairngorms National Park. The project encompasses green engineering woody structures and sediment management, as well as water margin management and riparian planting. The aim is to improve the capability of the watercourse to cope with high flow events, reduce excessive erosion and to protect in-channel and riparian habitats, as well as farm livelihoods. The works were carried out as a Scottish Rural Development Programme (SRDP) Agri-Environment Climate Scheme (AECS), supported and managed by a National Lottery Heritage Funded partnership (TGLP) as part of their wider ‘Our Water Environment’ project running across the Tomintoul and Glenlivet area. | ||
|Project title=River Avon Our Water Environment | |Project title=River Avon Our Water Environment |
Revision as of 15:42, 9 June 2020
This case study is pending approval by a RiverWiki administrator.
Project overview
Status | Complete |
---|---|
Project web site | |
Themes | Flood risk management, Habitat and biodiversity, Social benefits, Water quality |
Country | Scotland |
Main contact forename | Jos |
Main contact surname | Milner |
Main contact user ID | |
Contact organisation | |
Contact organisation web site | http://https://www.tomintoulandglenlivet.com/our-water-environment/ |
Partner organisations | Spey Fisheries Board, Cairngorms National Park Authority, Crown Estate Scotland, Delnabo Estate, Fordmouth Farm |
Parent multi-site project | |
This is a parent project encompassing the following projects |
No |
Project summary
River restoration works have been carried out along a high-energy reach of the River Avon within the River Spey Special Area of Conservation (SAC) in Cairngorms National Park. The project encompasses green engineering woody structures and sediment management, as well as water margin management and riparian planting. The aim is to improve the capability of the watercourse to cope with high flow events, reduce excessive erosion and to protect in-channel and riparian habitats, as well as farm livelihoods. The works were carried out as a Scottish Rural Development Programme (SRDP) Agri-Environment Climate Scheme (AECS), supported and managed by a National Lottery Heritage Funded partnership (TGLP) as part of their wider ‘Our Water Environment’ project running across the Tomintoul and Glenlivet area.
Monitoring surveys and results
Lessons learnt
Image gallery
Catchment and subcatchmentSelect a catchment/subcatchment
Catchment
Subcatchment
Other case studies in this subcatchment: Allt Lorgy River Restoration
Site
Project background
Cost for project phases
Reasons for river restoration
Measures
MonitoringHydromorphological quality elements
Biological quality elements
Physico-chemical quality elements
Any other monitoring, e.g. social, economic