Case study:Gilev's Grove reconstruction: Difference between revisions
No edit summary |
No edit summary |
||
Line 18: | Line 18: | ||
|Project picture=Image big 142436.jpg | |Project picture=Image big 142436.jpg | ||
|Picture description=General scheme of the Gilev's Grove | |Picture description=General scheme of the Gilev's Grove | ||
|Project summary=Reconstruction of a unique forest park, which is located between two water objects - the Klyuchi stream and Lake Krivoe - began in 2015 and ended in November of 2016. | |||
Objectives to be achived: | |||
1) Protection and restoration of the Klyuchi stream valley. The workers stabilized about 23 thousand square meters of slopes and re-designed the bed of the Klyuchi stream. New bridge-passage was built over the stream in the grove. After restoration works completion the unpleasant smell from the Klyuchi stream in the forest park was not traced anymore. | |||
2) Allocation of entertainment facilities: large picnic mangal-barbeque zone. 19 arbors were installed along the stream. Swings were mounted for kids between arbors. Sanitation facilities were put nearby as well. | |||
3)Installation of new playgrounds for children. They are designed for children of different ages and different interests. There are sandboxes and swings for toddlers and various sports equipment for tinagers. Comfortable benches installed carefully for parents throughout the gaming area. | |||
4) | |||
|Project title=Gilev's Grove reconstruction | |Project title=Gilev's Grove reconstruction | ||
}} | }} |
Revision as of 10:23, 15 February 2019
This case study is pending approval by a RiverWiki administrator.
Project overview
Status | In progress |
---|---|
Project web site | http://https://72.ru/text/gorod/294961606352896.html |
Themes | Habitat and biodiversity, Hydromorphology, Social benefits, Spatial planning, Water quality |
Country | Russia |
Main contact forename | Timur |
Main contact surname | Pavluk |
Main contact user ID | User:T.Pavluk |
Contact organisation | RosNIIVH |
Contact organisation web site | http://wrm.ru |
Partner organisations | |
This is a parent project encompassing the following projects |
Project summary
Reconstruction of a unique forest park, which is located between two water objects - the Klyuchi stream and Lake Krivoe - began in 2015 and ended in November of 2016.
Objectives to be achived:
1) Protection and restoration of the Klyuchi stream valley. The workers stabilized about 23 thousand square meters of slopes and re-designed the bed of the Klyuchi stream. New bridge-passage was built over the stream in the grove. After restoration works completion the unpleasant smell from the Klyuchi stream in the forest park was not traced anymore.
2) Allocation of entertainment facilities: large picnic mangal-barbeque zone. 19 arbors were installed along the stream. Swings were mounted for kids between arbors. Sanitation facilities were put nearby as well.
3)Installation of new playgrounds for children. They are designed for children of different ages and different interests. There are sandboxes and swings for toddlers and various sports equipment for tinagers. Comfortable benches installed carefully for parents throughout the gaming area.
4)
Monitoring surveys and results
Lessons learnt
Image gallery
Catchment and subcatchment
Site
Project background
Cost for project phases
Reasons for river restoration
Measures
MonitoringHydromorphological quality elements
Biological quality elements
Physico-chemical quality elements
Any other monitoring, e.g. social, economic
Monitoring documents
Additional documents and videos
Additional links and references
Supplementary InformationEdit Supplementary Information
|