{{Case study status
{{Case study status
|Approval status=Draft
|Approval status=Approved
}}
}}
{{Location
{{Location

Latest revision as of 16:39, 12 November 2018

0.00
(0 votes)


To discuss or comment on this case study, please use the discussion page.


Location: 47° 11' 25.66" N, 14° 46' 38.03" E
Loading map...
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.


Project overview

Edit project overview
Status Complete
Project web site http://www.murerleben.at/index.asp?pg_nr=60460&lang=en
Themes Environmental flows and water resources, Flood risk management, Habitat and biodiversity
Country Austria
Main contact forename Jörg
Main contact surname Raderbauer
Main contact user ID User:9984
Contact organisation freiland Environmental Consulting Civil Engineers Ltd.
Contact organisation web site http://www.freiland.at
Partner organisations Office of the Styrian Government - Department 14 Watermanagement, resources and sustainability
Parent multi-site project
This is a parent project
encompassing the following
projects
No
This case study hasn’t got a picture, you can add one by editing the project overview.

Project summary

Edit project overview to modify the project summary.


The project "Inner Alpine river basin management Upper Mur" was conducted within the framework of the EU funding program "LIFE-Nature" and focused on the restoration, improvement and long-term protection of the natural floodplains and the river landscape of the Upper Mur. The flood protection for the population of the Mur valley was an essential requirement. The measures cover the area of the three political districts Murau, Judenburg and Knittelfeld.

During the four-year project, more than 90 kilometers of the river were made passable for fish, seven cutoff meander and tributaries were revitalised or newly created. The "passive flood protection" - an important goal of water protection management - could be realised through purchasing and reactivation of approximately 17 ha retention areas alongside the river as flood inundation area. The recreation and adventure area on the river Mur was created or enhanced to 4 km of river length.

The total investment amount was about EUR 2.2 million, the EU financed 50% thereof. The national share has been taken over by the lead partner, the Government of Styria, represented by the Departments of Water Protection Management and Nature Protection, and other partners. Major funding has been provided by The Austrian Federal Ministry of Agriculture, Forestry, Environment and Water Management.

Monitoring surveys and results

This case study hasn’t got any Monitoring survey and results, you can add some by editing the project overview.

Lessons learnt

This case study hasn’t got any lessons learnt, you can add some by editing the project overview.


Image gallery


LIFE III (LIFE03 NAT/A/000011) „Inner-Alpine river basin management – Upper River Mur - murerleben I" 2003-2007 and LIFE+ (LIFE+ 08 NAT A 614) „Inner-Alpine river basin management – Upper River Mur - murerleben II" 2010-2015 ©freiland
ShowHideAdditionalImage.png


Catchment and subcatchment



Site

Name
WFD water body codes
WFD (national) typology
WFD water body name
Pre-project morphology
Reference morphology
Desired post project morphology
Heavily modified water body
National/international site designation
Local/regional site designations
Protected species present
Invasive species present
Species of interest
Dominant hydrology
Dominant substrate
River corridor land use
Average bankfull channel width category
Average bankfull channel width (m)
Average bankfull channel depth category
Average bankfull channel depth (m)
Mean discharge category
Mean annual discharge (m3/s)
Average channel gradient category
Average channel gradient
Average unit stream power (W/m2)


Project background

Reach length directly affected (m)
Project started 2003/08/01
Works started
Works completed
Project completed 2007/07/31
Total cost category 1000 - 5000 k€
Total cost (k€) 21252,125 k€ <br />2,125,000 € <br />
Benefit to cost ratio
Funding sources EU Life Programme (50%)

Cost for project phases

Phase cost category cost exact (k€) Lead organisation Contact forename Contact surname
Investigation and design
Stakeholder engagement and communication
Works and works supervision
Post-project management and maintenance
Monitoring



Reasons for river restoration

Mitigation of a pressure Flood risk management, Intensified farming around river banks
Hydromorphology Continuity for organisms, Quantity & dynamics of flow
Biology Fish: Abundance, Fish: Species composition
Physico-chemical
Other reasons for the project


Measures

Structural measures
Bank/bed modifications Creation of bars, Creation of Slips, Creation of undercut banks and islets, Creation of fish passes
Floodplain / River corridor Regeneration of alluvial forests, Creation of pond
Planform / Channel pattern Reconnection of water bodies to the river
Other
Non-structural measures
Management interventions
Social measures (incl. engagement)
Other


Monitoring

Hydromorphological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Biological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Physico-chemical quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative

Any other monitoring, e.g. social, economic

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative


Monitoring documents



Additional documents and videos


Additional links and references

Link Description

Supplementary Information

Edit Supplementary Information