Case study:Restore riparian floodplain habitats maintained in reserve "Dolna topchia" and run off on his sleeve "Malka Tundzha": Difference between revisions
No edit summary |
No edit summary |
||
(One intermediate revision by one other user not shown) | |||
Line 20: | Line 20: | ||
Through the construction of channel and water intake facility is carried out gravity connection between the river and sleeve " MalkaTundzha" by drainage channel along an existing irrigation canal that expanding, allowing hydration of 467.6 ha of habitat 91F0. The channel is lined and the bed of the "MalkaTundzha” will supply the groundwater in the area of the reserve. After the feedback between " MalkaTundzha " and river along the southern border of the reserve "Dolna topchia" will be implemented consistent circulation of water in reserve. | Through the construction of channel and water intake facility is carried out gravity connection between the river and sleeve " MalkaTundzha" by drainage channel along an existing irrigation canal that expanding, allowing hydration of 467.6 ha of habitat 91F0. The channel is lined and the bed of the "MalkaTundzha” will supply the groundwater in the area of the reserve. After the feedback between " MalkaTundzha " and river along the southern border of the reserve "Dolna topchia" will be implemented consistent circulation of water in reserve. | ||
}} | }} | ||
{{Image gallery}} | |||
{{Case study image | |||
|File name=Dolna topchia Reserve 1.jpg | |||
|Caption=Dolna topchia Reserve_1 | |||
}} | |||
{{Case study image | |||
|File name=Dolna topchia Reserve 2.jpg | |||
|Caption=Dolna topchia Reserve_2 | |||
}} | |||
{{Case study image | |||
|File name=Tundzha river 1.jpg | |||
|Caption=Tundzha river_1 | |||
}} | |||
{{Case study image | |||
|File name=Tundzha river 2.jpg | |||
|Caption=Tundzha river_2 | |||
}} | |||
{{Case study image | |||
|File name=Tundzha river 3.jpg | |||
|Caption=Tundzha river_3 | |||
}} | |||
{{Image_gallery_end}} | |||
{{Toggle button}} | |||
{{Toggle content start}} | |||
{{Case_study_subcatchment | {{Case_study_subcatchment | ||
|Subcatchment= | |Subcatchment= | ||
Line 163: | Line 187: | ||
}} | }} | ||
{{Measures | {{Measures | ||
|Floodplain / River corridor=Creation of wetland | |||
|Wider stakeholder / citizen engagement=Information provision | |||
|Floodplain / River corridor= | |||
|Wider stakeholder / citizen engagement= | |||
}} | }} | ||
{{Hydromorphological_quality_elements_header}} | {{Hydromorphological_quality_elements_header}} | ||
Line 215: | Line 225: | ||
{{Monitoring_documents}} | {{Monitoring_documents}} | ||
{{Monitoring_documents_end}} | {{Monitoring_documents_end}} | ||
{{Additional_Documents}} | {{Additional_Documents}} | ||
{{Additional_Documents_end}} | {{Additional_Documents_end}} | ||
Line 261: | Line 249: | ||
}} | }} | ||
{{Case_study_upload}} | {{Case_study_upload}} | ||
{{Toggle content end}} |
Latest revision as of 09:38, 1 June 2017
Project overview
Status | Complete |
---|---|
Project web site | |
Themes | Habitat and biodiversity |
Country | Bulgaria |
Main contact forename | Penka |
Main contact surname | Nacheva |
Main contact user ID | |
Contact organisation | Regional Inspectorate of Environment and Water – Stara Zagora |
Contact organisation web site | http://www.stz.riew.e-gov.bg/ |
Partner organisations | |
Parent multi-site project | |
This is a parent project encompassing the following projects |
No |
Project summary
Design and construction of hydraulic structures on river Tundzha for recovery of riparian wetland biotopes maintained in reserve "Dolna topchia" and run off on his sleeve "MalkaTundzha."
The main objective of the project is to restore the conditions necessary for the maintenance of riparian biotopes. Main habitat is riparian floodplain forest - habitat code 91F0. There is good population of spring snowflake. The target of the project area is maintained reserve category " Dolna topchia " and is part of the Natura 2000 network –protected area "Reka Tundzha 2." To achieve the objective was built weir on the Tundzha river and channel with length of 900 m. The water intake includes the diversion weir, stilling, primitive channel, fish passage and water intake facility.
Through the construction of channel and water intake facility is carried out gravity connection between the river and sleeve " MalkaTundzha" by drainage channel along an existing irrigation canal that expanding, allowing hydration of 467.6 ha of habitat 91F0. The channel is lined and the bed of the "MalkaTundzha” will supply the groundwater in the area of the reserve. After the feedback between " MalkaTundzha " and river along the southern border of the reserve "Dolna topchia" will be implemented consistent circulation of water in reserve.
Monitoring surveys and results
Lessons learnt
Image gallery
Catchment and subcatchmentSelect a catchment/subcatchment
Catchment
Subcatchment
Other case studies in this subcatchment: Restore riparian floodplain habitats maintained in reserve "Dolna topchia" and run off on his sleeve "Malka Tundzha"
Site
Project background
Cost for project phases
Reasons for river restoration
Measures
MonitoringHydromorphological quality elements
Biological quality elements
Physico-chemical quality elements
Any other monitoring, e.g. social, economic
Monitoring documents
Additional documents and videos
Additional links and references
Supplementary InformationEdit Supplementary Information
|