Case study:Restoration of Siuruanjoki River: Difference between revisions

From RESTORE
Jump to navigation Jump to search
No edit summary
No edit summary
 
(11 intermediate revisions by 7 users not shown)
Line 1: Line 1:
{{Case_study_status
{{Case study status
|Approval status=
|Approval status=Approved
   
 
 
   
      Draft
}}
}}
{{Location
{{Location
Line 14: Line 9:
|Themes=Land use management - agriculture, Land use management - forestry, Social benefits, Water quality
|Themes=Land use management - agriculture, Land use management - forestry, Social benefits, Water quality
|Country=Finland
|Country=Finland
|Main contact forename=-
|Main contact forename=Sanna
|Main contact surname=-
|Main contact surname=Pehkonen
|Contact organisation=Regional Environment Institute
|Contact organisation=Centre for Economic Development, Transport and the Environment for Lapland
|Multi-site=Yes
|Contact organisation url=www.ymparisto.fi/download.asp?contentid=68588
|Multi-site=No
|Project picture=Restoration1 of Siuruanjoki.jpg
|Project summary=Siuruanjoki River is located Northern part of Finland and is one of the tributaries of Iijoki River. The project ”Siuruanjoki kuntoon” (Making Siuruanjoki River Fit) objective was to apply various means of mitigate the diffuse loading impacts of a large watershed area within three municipalities in Northern Finland; i.e. within the Provinces of Lapland and Ostrobotnia. The project was carried out in Ostrobothnia in the years 2000-2006.
|Project summary=Siuruanjoki River is located Northern part of Finland and is one of the tributaries of Iijoki River. The project ”Siuruanjoki kuntoon” (Making Siuruanjoki River Fit) objective was to apply various means of mitigate the diffuse loading impacts of a large watershed area within three municipalities in Northern Finland; i.e. within the Provinces of Lapland and Ostrobotnia. The project was carried out in Ostrobothnia in the years 2000-2006.
   
   
Line 24: Line 21:
Among the achievements of the project were the formulation of overall forestry-related plans for the protection of the water system, trials with new peat-production-related methods of treating run-off water, formulation of property-specific plans for improving the treatment of waste water, and nutrient balance studies were created for farms along with the conducting of environmental assessments.  
Among the achievements of the project were the formulation of overall forestry-related plans for the protection of the water system, trials with new peat-production-related methods of treating run-off water, formulation of property-specific plans for improving the treatment of waste water, and nutrient balance studies were created for farms along with the conducting of environmental assessments.  
The project was mostly managed by Regional Environmental Agency of Ostrobothnia Pohjois-Pohjanmaan ymparistokeskus in close co-operation with local actors. The project had a total budget of € 630,705.
The project was mostly managed by Regional Environmental Agency of Ostrobothnia Pohjois-Pohjanmaan ymparistokeskus in close co-operation with local actors. The project had a total budget of € 630,705.
}}
}}
{{Image gallery}}
{{Case study image
|File name=Restoration of Siuruanjoki River Catchment of Siuruanjoki River.jpg
|Caption=Catchment of Siuruanjoki River
}}
{{Case study image
|File name=Restoration of Siuruanjoki River Bank reinforcement.jpg
|Caption=Bank reinforcement
}}
{{Case study image
|File name=Restoration of Siuruanjoki River Constructed sedimentation basin.jpg
|Caption=Constructed sedimentation basin
}}
{{Image_gallery_end}}
{{Toggle button}}
{{Toggle content start}}
{{Case_study_subcatchment
{{Case_study_subcatchment
|Subcatchment=
|Subcatchment=
Line 83: Line 94:
        
        
}}
}}
{{Project_background
{{Project background
|Reach length directly affected=
|Project started=2000/01/01
   
|Works completed=2006/01/01
   
|Total cost category=500 - 1000 k€
     
|Total1 cost=850 k€
|Project started=
|Funding sources=European Regional Development Fund,Regional Environment Institute,Cities of Pudasjärvi, Yli-Ii and Ranua
      2000/01/01
|Works started=
     
|Works completed=
      2006/01/01
|Project completed=
     
|Total cost category=
      500 - 1000 k€
|Total1 cost=
      850 k€
|Funding sources=
      European Regional Development Fund (ERDF),Regional eEnvironment Institutes,Cities of Pudasjärvi, Yli-Ii and Ranua
|Investigation and design cost category=
     
|Invst and design cost=
     
|Investigation and design Lead organisation=
     
|Investigation and design Other contact forename=
     
|Investigation and design Other contact surname=
     
|Stakeholder1 engagement cost category=
     
|stk engagement cost=
     
|Stakeholder engagement Lead organisation=
     
|Stakeholder engagement Other contact forename=
     
|Stakeholder engagement Other contact surname=
     
|Works1 and supervision cost category=
     
|Wrk and supervision cost=
     
|Works and supervision Lead organisation=
     
|Works and supervision Other contact forename=
     
|Works and supervision Other contact surname=
     
|Post-project1 management and maintenance cost category=
     
|Post-project2 management and maintenance cost=
     
|Post-project management and maintenance Lead organisation=
     
|Post-project management and maintenance Other contact forename=
     
|Post-project management and maintenance Other contact surname=
     
|Monitoring1 cost category=
     
|Monitoring2 cost=
     
|Monitoring Lead organisation=
     
|Monitoring Other contact forename=
     
|Monitoring Other contact surname=
     
|Supplementary funding information=
     
}}
}}
{{Motivations
{{Motivations
Line 170: Line 116:
}}
}}
{{Measures
{{Measures
|Bank and bed modifications measure=
|Floodplain / River corridor=Removal of embankments, Creation of wetland,establishment of woodland
   
|Social measures=Awareness raising
   
|Wider stakeholder / citizen engagement=Information provision,Participation in works,Participation in monitoring
     
|Floodplain / River corridor=
      removal of embankments,creation of wetlands,establishment of woodland
|Planform / Channel pattern=
     
|Other technical measure=
     
|Management interventions=
     
|Social measures=
      Awaress-raising
|Wider stakeholder / citizen engagement=
      Information provision,Participation in works,Participation in monitoring
}}
}}
{{Hydromorphological_quality_elements_header}}
{{Hydromorphological_quality_elements_header}}
Line 276: Line 209:
{{Monitoring_documents}}
{{Monitoring_documents}}
{{Monitoring_documents_end}}
{{Monitoring_documents_end}}
{{Image_gallery}}
{{Image_gallery_end}}
{{Additional_Documents}}
{{Additional_Documents}}
{{Additional_Documents_end}}
{{Additional_Documents_end}}
Line 298: Line 229:
}}
}}
{{Case_study_upload}}
{{Case_study_upload}}
{{Toggle content end}}

Latest revision as of 13:03, 1 November 2018

0.00
(0 votes)


To discuss or comment on this case study, please use the discussion page.


Location: 65° 24' 22.66" N, 25° 52' 29.76" E
Loading map...
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.


Project overview

Edit project overview
Status Complete
Project web site
Themes Land use management - agriculture, Land use management - forestry, Social benefits, Water quality
Country Finland
Main contact forename Sanna
Main contact surname Pehkonen
Main contact user ID
Contact organisation Centre for Economic Development, Transport and the Environment for Lapland
Contact organisation web site http://www.ymparisto.fi/download.asp?contentid=68588
Partner organisations
Parent multi-site project
This is a parent project
encompassing the following
projects
No
Project picture

Project summary

Edit project overview to modify the project summary.


Siuruanjoki River is located Northern part of Finland and is one of the tributaries of Iijoki River. The project ”Siuruanjoki kuntoon” (Making Siuruanjoki River Fit) objective was to apply various means of mitigate the diffuse loading impacts of a large watershed area within three municipalities in Northern Finland; i.e. within the Provinces of Lapland and Ostrobotnia. The project was carried out in Ostrobothnia in the years 2000-2006.

The project aim was to improve the quality of the water in Siuruanjoki River and the condition of the water system in such a way that it would be better suited to meet the needs of recreation, fishing, and tourism. The project was accomplished by mitigating the impacts of diffuse loading, restoring parts of the water system, and tending the river bank areas. The diffuse loading was mitigated by reducing the external loading from agriculture and forestry, and by improving the waste water treatment solutions used with regard to the rural population and holiday-home users. Lake Saunajarvi in the area of Pudasjarvi was restored by means of intensified fishing aimed at ridding the lake of undesirable and excessive fish species. In addition, the project included the central objective of adding to the environmental awareness and sense of responsibility of the local people.

Among the achievements of the project were the formulation of overall forestry-related plans for the protection of the water system, trials with new peat-production-related methods of treating run-off water, formulation of property-specific plans for improving the treatment of waste water, and nutrient balance studies were created for farms along with the conducting of environmental assessments. The project was mostly managed by Regional Environmental Agency of Ostrobothnia Pohjois-Pohjanmaan ymparistokeskus in close co-operation with local actors. The project had a total budget of € 630,705.

Monitoring surveys and results

This case study hasn’t got any Monitoring survey and results, you can add some by editing the project overview.

Lessons learnt

This case study hasn’t got any lessons learnt, you can add some by editing the project overview.


Image gallery


Catchment of Siuruanjoki River
Bank reinforcement
Constructed sedimentation basin
ShowHideAdditionalImage.png


Catchment and subcatchment

Catchment

River basin district Iijoki River basin
River basin Siuruanjoki River Basin

Subcatchment

River name Siuruanjoki River
Area category 1000 - 10000 km²
Area (km2) 2387 km²238,700 ha <br />
Maximum altitude category
Maximum altitude (m)
Dominant geology Organic (i.e. Peat)
Ecoregion Fenno-Scandian Shield
Dominant land cover bog
Waterbody ID



Site

Name Catchment of Siuruanjoki River
WFD water body codes
WFD (national) typology
WFD water body name
Pre-project morphology
Reference morphology
Desired post project morphology
Heavily modified water body
National/international site designation
Local/regional site designations multiple designations across the site
Protected species present
Invasive species present
Species of interest
Dominant hydrology
Dominant substrate
River corridor land use Coniferous plantation
Average bankfull channel width category
Average bankfull channel width (m)
Average bankfull channel depth category
Average bankfull channel depth (m)
Mean discharge category
Mean annual discharge (m3/s)
Average channel gradient category
Average channel gradient
Average unit stream power (W/m2)


Project background

Reach length directly affected (m)
Project started 2000/01/01
Works started
Works completed 2006/01/01
Project completed
Total cost category 500 - 1000 k€
Total cost (k€) 850 k€850,000 € <br />
Benefit to cost ratio
Funding sources European Regional Development Fund, Regional Environment Institute, Cities of Pudasjärvi, Yli-Ii and Ranua

Cost for project phases

Phase cost category cost exact (k€) Lead organisation Contact forename Contact surname
Investigation and design
Stakeholder engagement and communication
Works and works supervision
Post-project management and maintenance
Monitoring



Reasons for river restoration

Mitigation of a pressure Riparian development
Hydromorphology Continuity for organisms, Structure & condition of riparian/ lake shore zones
Biology Fish: Abundance, Fish: Species composition
Physico-chemical Nutrient concentrations
Other reasons for the project


Measures

Structural measures
Bank/bed modifications
Floodplain / River corridor Removal of embankments, Creation of wetland, establishment of woodland
Planform / Channel pattern
Other
Non-structural measures
Management interventions
Social measures (incl. engagement) Awareness raising
Other Information provision, Participation in works, Participation in monitoring


Monitoring

Hydromorphological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative
[[]]

Biological quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative
[[]]

Physico-chemical quality elements

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative
[[]]

Any other monitoring, e.g. social, economic

Element When monitored Type of monitoring Control site used Result
Before measures After measures Qualitative Quantitative


Monitoring documents



Additional documents and videos


Additional links and references

Link Description

Supplementary Information

Edit Supplementary Information