Case study:Rio Tepice urban restoration: Difference between revisions
Jump to navigation
Jump to search
m (A.goltara moved page Case study:Rio Tepice stream urban requalification - Chieri to Case study:Rio Tepice urban restoration) |
No edit summary |
||
(2 intermediate revisions by one other user not shown) | |||
Line 1: | Line 1: | ||
{{ | {{Case study status | ||
|Approval status= | |Approval status=Approved | ||
}} | }} | ||
{{Location | {{Location | ||
Line 93: | Line 88: | ||
}} | }} | ||
{{Measures | {{Measures | ||
|Bank and bed modifications measure= | |Bank and bed modifications measure=Bank improvement, | ||
|Floodplain / River corridor=Riparian | |Floodplain / River corridor=Riparian planting | ||
|Management interventions=Management of paths | |Management interventions=Management of paths | ||
|Social measures=Public green area | |Social measures=Public green area | ||
|Wider stakeholder / citizen engagement=Participation in monitoring | |Wider stakeholder / citizen engagement=Participation in monitoring | ||
}} | }} |
Latest revision as of 13:38, 1 June 2017
Location: 45° 0' 36.17" N, 7° 49' 2.28" E
Left click to look around in the map, and use the wheel of your mouse to zoom in and out.
Project overview
Status | Complete |
---|---|
Project web site | |
Themes | Habitat and biodiversity, Social benefits, Spatial planning, Urban |
Country | Italy |
Main contact forename | Guido |
Main contact surname | Blanchard |
Main contact user ID | |
Contact organisation | Studio Blanchard-Gallo |
Contact organisation web site | http://www.coqblanc.it/ |
Partner organisations | |
Parent multi-site project | |
This is a parent project encompassing the following projects |
No |
Project summary
Edit project overview to modify the project summary.
This project concerned the restoration of a stretch of Rio Tepice in the urban area of Chieri (TO) through this kind of actions:
- restoration (cutting, new plantations with autochthonous species, bioengineering works) of the riparian vegetation and of the river banks;
- revegetation of an area of 1.08 hectares;
Moreover new footpaths adjacent to the watercourse were created.
Monitoring surveys and results
This case study hasn’t got any Monitoring survey and results, you can add some by editing the project overview.
Lessons learnt
This case study hasn’t got any lessons learnt, you can add some by editing the project overview.
Image gallery
Catchment and subcatchmentSelect a catchment/subcatchment
Catchment
Subcatchment
Site
Project background
Cost for project phases
Reasons for river restoration
Measures
MonitoringHydromorphological quality elements
Biological quality elements
Physico-chemical quality elements
Any other monitoring, e.g. social, economic
Monitoring documents
Additional documents and videos
Additional links and references
Supplementary InformationEdit Supplementary Information
|